Once a budget cycle is locked, a change to its forecasts goes through a change request. Your changes collect in a draft, Your pending changes, until you submit them with a reason. The budget changes only when owner or finance approves. Owners, finance and program managers file change requests.

The result: your changes are with the approvers, with a reason and their impact on your program’s budget, and you are told by email when they decide.

1. Make the change

Open the forecast and change it as usual, or add a new one. When the change would alter the locked budget, Zeno Budget refuses the save and offers Add to change request (or Propose deleting it). Choose it. The change is added to Your pending changes: Added to your pending changes. The budget changes once the request is submitted and approved. Add as many changes as belong together. Each is a line of your draft.
Push the Youth Mentoring summer camp from June to July and cut it to $14,000. The budget is locked, so add it to my change request.

2. Check the impact

Open Change requests and select Your pending changes. Each line shows the forecast, program, category, the change (for example $18,000 → $14,000, from Jun 1 to Jul 1) and its effect Over the cycle. Impact shows what the lines do to your program, category by category and month by month, ending in Program net, with a headline such as The budget spends $4,000 less over the cycle. Owners and finance also see the organization’s cash week by week. Tick and untick lines to see the impact of some of them. To fix a line, choose Change; saving replaces that line. Remove takes it out.

3. Submit it

Under Submit for approval, give it a Title (what it changes, in a few words) and a Why (what the approver should know). Choose Submit, or Submit k of n to submit only the ticked lines; the rest stay behind in a new draft. Owner and finance are emailed. The budget does not change until one of them approves.

Follow it

The request’s Timeline records each step: submitted, comments, the decision. You can Add a comment, which emails the approvers.
  • Remind the approvers emails them again, once a day at most.
  • Withdraw stops the request waiting for a decision; the budget stays as it is.
You are emailed when the request is approved, partly approved, rejected or sent back.

If it is sent back

The status reads Sent back for revisions, with the approver’s comment. Change or remove lines, then choose Submit it again.

If it is partly approved

Some lines went into the budget and the rest were rejected. The request shows which, line by line, as Approved or Not approved, and the byline shows how much was approved. File a new request for anything you still want.

When a change is refused outright

A change that would move forecasts in two locked cycles at once is refused. Split it by date: end the forecast at the first cycle’s close, and propose the rest as a new forecast in the second.